Showing 25 results of 850.

Event Company Location Fuel acceptance, % Event Date From Event Date Till Event Duration Event Publication Date
Additional information
The demand for biomass has decreased due to the weather conditions Kauno energija AB (buvusi Petrašiūnų kat.) 80 % 2019-10-21 2019-10-27 7 days 2019-10-15 15:28:28 Biomass consumption decreased regarding the weather conditions, though biomass delivery is limited to 80% during week 43 for all active half-year transactions.
The demand for biomass has decreased due to the weather conditions Šiaulių energija AB 80 % 2019-10-14 2019-10-20 7 days 2019-10-14 11:24:29 Ryšium su neįprastai šiltais orais AB "Šiaulių energija" Tilvyčio katilinės (Tilvyčio g. 15, Kuršėnai) 42 savaitę biokuro poreikis mažinamas 20 procentų. Pagal sutartį Nr. SUT042492.
The demand for biomass has decreased due to the weather conditions Šiaulių energija AB 80 % 2019-10-14 2019-10-20 7 days 2019-10-10 16:40:33 Biomass consumption decreased regarding the weather conditions, though biomass delivery is limited to 80% during week 42 for all active half-year transactions.
The demand for biomass has decreased due to the weather conditions Kauno energija AB (buvusi Petrašiūnų kat.) 80 % 2019-10-14 2019-10-20 7 days 2019-10-09 16:04:13 Biomass consumption decreased regarding the weather conditions, though biomass delivery is limited 20 % during week 42 for all active transactions.
Lost heat auction Idex Baltic UAB 104A Taikos pr. Kaunas 0 % 2019-10-14 2019-10-27 14 days 2019-10-07 15:46:11 Boiler house won't work.
Other Gren Akmenė UAB 2019-10-07 2019-10-14 8 days 2019-10-07 11:22:15 Regarding the started heating season in 2019-10-01, there is a need for a delivery start of quarterly agreements.
Other Vilniaus šilumos tinklai, AB 2019-10-21 2019-10-21 1 days 2019-10-04 09:52:45 Vilnius Heat Networks, AB update on 17.09.2019 Please be advised that after scheduled repairs, fuel acceptance will resume on Monday, 21 October 2019.
Other Panevėžio energija AB 2019-10-09 2019-10-09 1 days 2019-10-03 15:43:04 Informuojame, kad visi tiekėjai, turintys pusmetines žiemos sutartis (pusmečio ir/arba ketvirčio), nuo W41 savaitės vidurio, t. y. nuo 2019-10-09 turi pradėti tiekti, tolygiai padieniui, sutartinį savaitinį biokuro kiekį į Rokiškio ŠTR Rokiškio RK pagal "žiemines" pusmetines sutartis, kadangi prasideda šildymo sezonas. Biokuro tiekimo grafikai dėl W41 yra pateikti tiekėjams internete.
Other Panevėžio energija AB 2019-10-01 2019-10-01 1 days 2019-09-26 11:24:33
Other Panevėžio energija AB 2019-10-01 2019-10-01 1 days 2019-09-26 11:24:21
Failure or planned repair of heating plants Panevėžio energija AB 191 Pušaloto g., Panevėžys 60 % 2019-09-25 2019-10-05 11 days 2019-09-25 16:51:41 Regarding equipment failure at Panevėžio RK-1 (boiler No. 6), during W40 all biomass deliveries are limited to 40 %. 60 % of the contracted W40 biomass will be accepted delivering it equally throughout 40th calendar week.
Other Panevėžio energija AB 2019-09-30 2019-09-30 1 days 2019-09-25 10:12:38 For biomass sellers information, H02 contracts will be activated from week 40 for delivery to Panevėžio RK-1, regarding the early start of the heating season. Delivery schedules are sent to biomass sellers. Biomass delivery is effected evenly.
Failure or planned repair of heating plants Alytaus šilumos tinklai UAB Pramonės g. 9, Alytus, Lietuva 80 % 2019-09-23 2019-09-25 3 days 2019-09-25 10:08:09 Biomass delivery will be organized on week 41.
Failure or planned repair of heating plants Orion Global PET UAB Metalo g. 16, Klaipėda 94100, LT 0 % 2019-09-18 2019-12-02 76 days 2019-09-23 08:56:04
Failure or planned repair of heating plants Vilniaus šilumos tinklai, AB Elektrinės g. 2, Vilnius, Lietuva 0 % 2019-10-12 2019-10-24 13 days 2019-09-17 13:55:10 Planned repairs of biomass consuming equipment. Due to unforeseen circumstances repair date has changed. Information will be updated. Biomass delivery for W42 will be individually negotiated with suppliers. Biomass acceptance expected from 23rd of October.
Other Kauno energija AB 2019-08-01 2019-08-04 4 days 2019-08-01 16:22:35 Due to hydraulic maintanance in Inkaro boiler house (Raudondvario 7-th track 4), heating zone, boiler house capacity from 2019-08-01 8:00 hour is limited to 8 MW. Biomass supply demand is reduced to 60 toe and postponed to 32nd delivery week.
Other Kauno energija AB 2019-07-26 2019-07-26 1 days 2019-08-01 16:13:39
Other Kauno energija AB 2019-07-25 2019-07-29 5 days 2019-07-25 13:20:30 About 12:30 biomass weighing scales broke down in Inkaro boiler house at Raudondvario 7th Trail 4, Kaunas. Until the failure is fixed, biomass will be weighed at Šilko boiler house at Varnių str. 48, Kaunas. Information will be update regarding to the fact.
Other Kauno energija AB 2019-07-23 2019-07-23 1 days 2019-07-23 13:06:30 2019-07-23 12:35 Inkaro boiler house at Raudondvario 7th Trail 4, Kaunas, biomass scale fault has been eliminated.
Other Kauno energija AB 2019-07-23 2019-07-29 7 days 2019-07-23 10:22:09 About 9:30 biomass weighing scales broke down in Inkaro boiler house at Raudondvario 7th Trail 4, Kaunas. Until the failure is fixed, biomass will be weighed at Šilko boiler house at Varnių str. 48, Kaunas. Information will be update regarding to the fact.
Failure or planned repair of heating plants Foksita UAB Chemijos g. 15b, Kaunas, Lietuva 0 % 2019-08-01 2019-08-14 14 days 2019-07-10 17:12:57 Biomass truck scales planned repair. Biomass regard W31 transactions should be delivered in July 29-31 period. .
Failure or planned repair of heating plants Vilniaus šilumos tinklai, AB Elektrinės g. 2, Vilnius, Lietuva 40 % 2019-07-09 2019-07-11 3 days 2019-07-09 11:47:29 Biomass boiler failure. This week biomass supply regarding valid transactions is reduced to 40%. The remaining biomass quantity regarding valid transactions will be accepted throughout next week.
Other Kauno energija AB 2019-06-28 2019-07-02 5 days 2019-06-28 11:43:48 About 9:30 biomass weighing scales broke down in Šilko boiler house at Varnių str. 48, Kaunas. Failure has been registered in the register of the suppliers of the scales. Until the failure is fixed, biomass will be weighed at the Inkaro boiler house at Raudondvario 7th Trail 4, Kaunas.
Other Kauno energija AB 2019-06-25 2019-06-30 6 days 2019-06-21 10:33:15 Due to IX stage 2 zone hydraulic tests and scheduled maintenance repair in Kaunas city district heating network from 2019-06-25 until 2019-06-30 planned average Inkaro boiler house daily production is approx. 6-7 MW per hour. Biomass consumption approx. 30 %. The remaining quantity of biomass by the contracts SUT042264 and SUT042258 will be evenly divided throughout 27th and 28th calendar weeks.
Failure or planned repair of heating plants Orion Global PET UAB Metalo g. 16, Klaipėda 94100, LT 0 % 2019-06-13 2019-06-30 18 days 2019-06-14 10:57:15 Due to the failure of biomass boiler equipment, the supply of biomass will be limited to 0% from 14.06.2019. The information will be updated according to the facts of the equipment repair results.